Roof flashings, or sheet metal bends, finish the details of the roof – the ridge, eaves, verges, valleys and abutments to walls and chimneys. TOODE makes standard flashings and bends to your drawing and dimensions – from the same material and in the same colour as the roofing. On request, we also make bends from copper sheet.
The main roof flashings
| Element |
Where and why |
| Ridge |
Closes the top of the roof and keeps moisture, dust and insects out from under the roofing. On low-pitched roofs a ridge seal is fitted with the ridge; a ventilated ridge seal is also available. |
| Verge |
Closes the side edge of the roof so that rainwater cannot get under the roofing from the side. The Classic roof has its own verge flashing. |
| Eaves flashing |
At the bottom edge of the roof, it leads water from the roofing into the gutter and protects the fascia boards from moisture. |
| Valley |
Collects and drains water in the internal corner where two roof slopes meet. |
| Abutment |
A watertight joint between the roofing and a vertical wall, chimney or higher terrace. |
| Window sill, parapet, corners |
External window sills, parapet cappings, external and internal corners, transitions and cover strips for roofs and facades. |
See the full list with drawings on the Standard flashings page. The dimensions, angles and shape of all standard elements can be changed to suit a specific roof.
Flashings to your drawing
If you need a non-standard bend, we will make it to your drawing and dimensions – for a roof, a facade or another project.
Prepare a drawing
Give the exact dimensions and bend angles, the material thickness (if you know it), which way the coloured side faces, the colour code and the quantity you need.
Send it to our sales team
Send the drawing to your TOODE sales contact by e-mail, or visit your nearest sales point for advice in person.
Get a quote
A specialist will review the drawing, confirm the details and tell you the production options, lead time and price.
Basic principles of installing flashings
- Eaves flashing – fixed to the first batten before the roofing, with a 50 mm overlap between flashings. It is best to install the gutter brackets before the eaves flashing.
- Valley – installed before the roofing, from the bottom up, with an overlap of at least 200 mm. The roofing on each slope must leave at least 200 mm of the valley free for water to run off.
- Verge – installed from the bottom up, with an overlap of at least 50 mm.
- Ridge – installed last, once the roofing is laid; fixed to the top of the profile with screws with sealing washers.
- Wall abutment – the top edge of the sheet is inserted into a groove in the wall and filled with sealant. Every joint must be made so that water runs down over the top of the sheet, not under it.
Screw sizes, fixing spacing and overlaps differ for each profile – you will find them on the metal roofing pages, under the “Flashings” tab.
Material and colours
We make flashings from the same steel and with the same coatings as the roofing – Polyester, Matt Pol, Pural BT, Pural BT Matt, PVDF and PVC. This means they are available in the colour of your roof; see the shades in the colour chart. You can order flashings together with the roofing, the rainwater system and other materials in one quote.
Frequently asked questions
Can flashings be made to my dimensions?
Yes. The dimensions, angles and shape of standard elements can be changed, and completely non-standard bends are made to your drawing. Send the drawing to our sales team or bring it to your nearest TOODE sales point.
What should the drawing include?
The exact dimensions and bend angles, the material thickness (if known), which way the coloured side faces, the colour code and the quantity. The more precise the information, the faster we can prepare a quote.
Will the flashings be the same colour as the roof?
Yes. They are made from the same material and with the same coatings as TOODE roofing, so the colour and surface match.
What is a roof abutment flashing?
It is a sheet metal bend that makes a watertight joint between the roofing and a vertical wall or chimney. Its top edge is inserted into a groove in the wall and sealed so that water cannot get under the roofing.
How do I install a verge flashing?
The verge is installed from the bottom of the roof upwards with an overlap of at least 50 mm. It covers the edge of the roofing and is fixed both to the verge board and through the roofing to the battens – the exact screw spacing is given in the installation guide for the specific profile.
How do I install an eaves flashing?
The eaves flashing is fixed to the first batten before the roofing is laid, with a 50 mm overlap between pieces. It is best to install the gutter brackets before the eaves flashing.
How do I install valleys?
Valleys are installed before the roofing, from the bottom up, with an overlap of at least 200 mm. The roofing on each slope must leave at least 200 mm of the valley free so that water can run off.