TP15 is used for wall cladding only and comes in three versions: TP15 A and TP15 B – classic trapezoidal profile versions, TP15 V – with an extra decorative fold in the middle of the panel that gives the facade visual variety.
The installation principle of TP15 is simple, but a few specific requirements must be followed – especially the size of the overlap for galvanised panels and the ban on abrasive cutting tools.
Delivery and storage
When receiving the goods, check that all ordered materials have been delivered and that there is no transport damage. Report any shortages or damage to the seller immediately – the recipient’s signature on the delivery note is binding, and later claims may not be considered. Damaged panels must not be installed!
- Store the panels on crossbeams at least 20 cm above the ground.
- Coloured panels in sealed packaging – for no longer than four weeks.
- Galvanised panels in sealed packaging outdoors – for no longer than one week (in damp weather white rust can form faster).
Important: TP15 sheets are thin steel (0.45-0.70 mm) and bend more easily than thicker profiles. Always lift and carry the panels – never drag them! Never hold a panel by the two ends only – it must also be supported in the middle to prevent bending.
Subframe and preparing for installation
Before installation, check that the wall frame or subframe is straight and rigid. The subframe can be a timber or metal profile system – the main thing is that it is stable, level and well fixed to the wall structure of the building.
- For a timber subframe, use dry timber min. 22×50 mm.
- The subframe spacing depends on the panel thickness and the wind load – consult our specialists.
- At corners and window and door openings, install the corresponding flashings before the panels.
Installing the panels
Start the installation from the right-hand side of the wall or with the longest panel – this makes it easier to keep the panels straight and perpendicular to the bottom edge of the wall.
- Install the panels perpendicular to the bottom edge of the wall (horizontal installation) or parallel to the edge (vertical installation).
- The side overlap is usually half a wave. If the joint has to be watertight, the overlap must be one wave, or a sealing tape or sealant must be used. Note: a one-wave overlap must not be used for galvanised panels – zinc corrosion can damage the overlap.
- Lengthwise overlap (if panels have to be joined lengthwise): at least 100 mm, over the subframe. At the joint, every wave is fixed to the subframe.
- Fix side overlaps and flashings with screws or blind rivets at a spacing of no more than 500 mm.
Screws and fixing rules
| Screw type |
Use |
Consumption |
| 4.8×25 mm with sealing washer |
Fixing panels to a timber subframe (through the bottom of the wave) |
~6 pcs/m² |
| 4.8×19 mm with sealing washer or blind rivet |
Fixing side overlaps and flashings |
spacing up to 500 mm |
Cutting and coating care
Use tin snips or other non-abrasive tools to cut the panels. Never use an abrasive cutting tool (an angle grinder with a cutting disc) – heat and sparks damage the coating and cause corrosion at the cut edges.
- Brush away metal filings immediately after cutting – the filings rust and can damage the coating nearby.
- Small areas of coating damage can be covered with special touch-up paint in the matching colour.
- Dirty panels can be cleaned with ordinary household cleaning products – solvents and aggressive chemicals are not allowed.
Safety at work
Always wear work gloves – the edges of TP15 panels are sharp. Low-profile sheets bend more easily and are more awkward to carry – take care when lifting panels at height.